NEWS from B220

Upcoming work on construction site B220

The area between B204 and B221, will within the coming weeks be given a new layer of gravel. This layer of gravel will be vibrated to make sure it is stable. This may cause noise and vibration disturbance to the surrounding buildings.

We attempt to do this as quickly as possible!

The excavation of B220 is almost complete. 23,000 tons of soil has been removed on approximately 1,300 truckloads. The soil has been deposited north of DTU on Hempelgrunden.

Next there will be a change in the area between the B204 and B221, where machines and gear are moved to the site and preparations of soil and sheet piling for B205 will start. More info about this follows.

If any questions, please contact project manager David Klubien on davidk@dtu.dk