News about 2nd Quadrant

The project leaders of CFB building 220 have informed us that the bunging will start this week. The first bung plates will be placed starting Wednesday August 20th and will last until the beginning of September.
 
The work involves noise and vibration. We strive to do it as fast as possible.
Thank you for your patience.

 

News about 3rd Quadrant

The project manager from AGROA reported that on Friday the August 15th the last pole was “beaten” into the ground. This means that there will be a change on the construction site in the form of restructuring and the establishment of sewer and cast foundations and ground slab.

This calls for increased attention as there will still be heavy traffic in the area.